Mellitah Bouri Gas Project: Libya’s $1.6bn Offshore Milestone 2026

Mellitah Bouri gas project has surpassed its scheduled progress milestone, reaching 69% overall completion against a target of 62%, with manufacturing and assembly of major offshore equipment now finalised in Italy ahead of shipment to the Libyan field.

The $1.565 billion development — awarded to Saipem in August 2023 — is Libya’s largest active upstream investment. By end-2025, approximately $928 million had already been deployed against the total budget, according to project announcements from Mellitah Oil and Gas, the joint venture between Eni and the National Oil Corporation (NOC) of Libya.

An official handover ceremony in Ravenna, Italy marked the completion of the fabrication phase, after which key platform components were loaded for offshore transit to the Bouri field. Arrival was expected within approximately ten days of the May 2026 ceremony.

Mellitah Bouri Gas Project: What the Infrastructure Involves

The Bouri field lies offshore Libya in the Mediterranean, with the development centred on gas exploitation from a field that has historically flared associated gas. The project involves the installation of new processing units on Platforms 3 and 4, compressors at the Sabratha offshore platform, and new subsea pipelines connecting the field to Sabratha and onward to the Mellitah industrial complex on the Libyan coast.

Designed to process up to 125 million cubic feet per day (MMscf/d) of gas, the project is not a storage or LNG terminal play — it is an offshore gas processing and gathering system. Once operational, production flows onshore to the Mellitah complex, which handles gas processing and feeds both domestic supply and the Greenstream pipeline that carries Libyan gas to Italy.

With heavy lifting and installation works on Platforms 3 and 4 now the next phase, the critical path runs through the second half of 2026. First gas production is targeted for September 2026, according to Libyan energy analyst Mahmud Mohammed.

Bouri Gas Project Timeline and Contract Scale

Saipem secured the engineering, procurement, construction and installation (EPCI) contract in August 2023. The project sits within the broader Mellitah Bouri gas project scope and represents one of the most complex offshore EPCI programmes currently active in the Mediterranean basin.

The scale places it alongside major regional schemes tracked in the $80 billion pipeline and infrastructure project pipeline globally, though the Bouri development is specifically oriented toward upstream processing rather than transmission. Subsea pipeline work connecting the offshore platforms to Sabratha is a critical integration element, given Sabratha’s role as the primary offshore hub feeding Greenstream.

Capital deployment of $928 million through end-2025 — roughly 59% of the total budget — indicates a project on track financially as well as physically, with the heaviest spend phases (heavy lift installation) now approaching.

Libya’s Gas Flaring Reduction Target and NOC Strategy

The NOC has committed to eliminating routine gas flaring by 2030. The Mellitah Bouri gas project directly supports that target by monetising gas volumes that have historically been flared at the Bouri field rather than processed and exported.

Libya produced approximately 900,000 barrels of oil per day in early 2026, with gas production constrained by ageing infrastructure and decades of underinvestment. The Bouri development is one of a small number of active large-scale upstream projects in the country, where political instability has historically deterred capital commitments at this scale.

For Eni — which operates the Greenstream pipeline and holds a long-standing position in Libyan upstream through the Mellitah JV — the project advances gas supply security for its Italian downstream operations. The Mellitah complex at the Libyan coast is the onshore reception and processing hub for multiple offshore fields feeding the Greenstream system.

What Comes Next for the Mellitah Bouri Gas Project

Following the completion of fabrication in Italy and component shipment, the project moves into the offshore heavy lift and installation phase. Platforms 3 and 4 will receive the new processing modules, and subsea pipeline tie-ins will be completed to connect the expanded offshore network to the Sabratha platform.

The September 2026 first gas target gives the project a tight but achievable execution window. Offshore installation campaigns in the Mediterranean are weather-dependent, and Libya’s political environment adds a layer of execution risk that does not affect most comparable projects. Mellitah and Saipem have not disclosed a formal schedule buffer.

A company profile for Mellitah Oil and Gas does not currently exist on this site — one is planned as a follow-up to this article to cover the JV structure, the full Libyan upstream portfolio, and the Greenstream pipeline relationship.

What is the Mellitah Bouri gas project?

The Mellitah Bouri gas project is a $1.565 billion offshore gas development in the Mediterranean off Libya, awarded to Saipem in August 2023. It involves installing gas processing units on Platforms 3 and 4, compressors at the Sabratha platform, and new subsea pipelines feeding onshore to the Mellitah industrial complex. Designed capacity is 125 MMscf/d, with first gas targeted for September 2026.

Who owns and operates the Mellitah Bouri gas project?

Mellitah Oil and Gas, a joint venture between Eni and Libya’s National Oil Corporation (NOC), owns and operates the development. Saipem holds the EPCI contract for the offshore installation work, covering platform modules, subsea pipelines, and compressor systems.

What is the current progress of the Bouri gas project in 2026?

As of May 2026, overall project completion stands at 69%, ahead of the planned 62% milestone. Manufacturing and assembly of major platform equipment was finalised in Ravenna, Italy, with components shipped offshore. The project now moves into heavy lift and installation on Platforms 3 and 4.

How does the Bouri field connect to Libyan gas exports?

Gas processed at the Bouri field travels via subsea pipeline to the Sabratha offshore platform, then onshore to the Mellitah industrial complex. From Mellitah, gas feeds the Greenstream pipeline, which runs under the Mediterranean to Sicily and onward into the Italian gas network. Eni operates Greenstream and holds a stake in the Mellitah JV.

Why is the Mellitah Bouri project significant for Libya’s gas sector?

The project targets routine gas flaring elimination at the Bouri field, aligned with NOC’s 2030 zero-flaring commitment. At 125 MMscf/d of processing capacity, it materially increases Libya’s ability to monetise offshore gas that has historically been wasted. It is one of the largest active upstream capital programmes in Libya and the Mediterranean basin.

Richard Hartleyhttps://www.oilgasstoragenews.com
Richard Hartley — Editor, Oil & Gas Storage News Richard Hartley is the Editor of Oil & Gas Storage News, a specialist B2B publication covering tank terminals, LNG infrastructure, pipelines, and energy storage worldwide. He covers the full value chain — from upstream storage and midstream logistics through to downstream terminal operations — with a focus on market developments, company profiles, and infrastructure projects that matter to working professionals. Richard's reporting draws on industry data, operator announcements, and project filings to deliver technically credible news and analysis. He is based in Houston, Texas